An internal auditor is reviewing key phases of a software development project. Which of the following would; the auditor most likely use to measure the project team's performance related to how project tasks are completed?


A.

A balanced scorecard.


B.

A quality audit


C.

Earned value analysis.


D.

Trend analysis