Summer Sale Limited Time 65% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: pass65

Exam IIA-CIA-Part3 All Questions
Exam IIA-CIA-Part3 All Questions

View all questions & answers for the IIA-CIA-Part3 exam

IIA CIA IIA-CIA-Part3 Question # 82 Topic 9 Discussion

IIA-CIA-Part3 Exam Topic 9 Question 82 Discussion:
Question #: 82
Topic #: 9

A organization finalized a contract in which a vendor is expected to design, procure, and construct a power substation for $3,000,000. In this scenario, the organization agreed to which of the following types of contracts?


A.

A cost-reimbursable contract.


B.

A lump-sum contract.


C.

A time and material contract.


D.

A bilateral contract.


Get Premium IIA-CIA-Part3 Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.