IIBA Certified Business Analysis Professional CBAP Question # 123 Topic 13 Discussion

CBAP Exam Topic 13 Question 123 Discussion:
Question #: 123
Topic #: 13

Gary is the business analyst for his organization. He has realized that he has overlooked a key group of stakeholders during the conduct stakeholder analysis process.

What is the danger in overlooking a key set of stakeholders?


A.

The newly identified stakeholders will now have to pay for any requirements they want to add to the requirements.


B.

The newly identified stakeholders will need to spend extra time to learn about the project and how it will affect them.


C.

The newly identified stakeholders will be excluded from decisions that affect the deliverables that have already been created in the project.


D.

The newly identified stakeholders may have requirements that require additions to the project or may nullify other requirements already in the project.