A project manager (PM) is planning the project timelines along with a business analyst (BA), and they come across the task of requirement allocation. The PM wants to know what the dependencies are before the requirement allocation task is initiated and seeks the BA's advice. Which of the following is a dependency that the BA will highlight as a prerequisite for requirement allocation?


A.

Design options are available


B.

Solution approach has been determined


C.

Requirements architecture is approved


D.

Stakeholders are identified