IIBA Certification of Capability in Business Analysis CCBA Question # 55 Topic 6 Discussion

CCBA Exam Topic 6 Question 55 Discussion:
Question #: 55
Topic #: 6

You have been assigned as the Project Manager for a new project that involves the development of a new interface for your existing time management system. You would like to plan the communications that need to be made during the project lifecycle. Which of the following would be a critical tool/technique to help in your communications planning?


A.

RAM Chart


B.

Affinity Diagram


C.

Stakeholder Analysis


D.

Text-Oriented Chart