A business owner has identified a high-priority requirement that needs to be implemented immediately. The project manager has asked the business analyst (BA) to conduct an impact analysis of this change. Which factor will the BA need to consider?


A.

Selection of the elicitation techniques for the requirement.


B.

Number of systems being affected by the requirement.


C.

Original source of the requirement.


D.

Method of requirement communication.