In the context of ISA/IEC 62443, maintenance activities by IACS Maintenance Service Providers generally begin after the solution (such as a control system or automation project) is handed over to the asset owner. This marks the transition from project (installation and commissioning) to operational maintenance, which includes patching, updating, and other support activities as part of the system lifecycle.