Question #: 36
Topic #: 4

Part of your change management plan details what should happen in the change control system for your project. Theresa, a junior project manager, asks what the configuration management activities are for scope changes. You tell her that all of the following are valid configuration management activities except for which one


A.

Configuration Item Costing


B.

Configuration Identification


C.

Configuration Verification and Auditing


D.

Configuration Status Accounting