The Disaster Recovery Manager should also be a member of the team that assisted in the development of the Disaster Recovery Plan. Senior-level management need to support the process but would not be involved with the initial process.
The following answers are incorrect:
Chief Information Officer. Is incorrect because the Senior-level management are the ones to authorize the recovery plan and process but during the initial recovery process they will most likely be heavily involved in other matters.
Chief Operating Officer. Is incorrect because the Senior-level management are the ones to authorize the recovery plan and process but during the initial recovery process they will most likely be heavily involved in other matters.
Chief Executive Officer. Is incorrect because the Senior-level management are the ones to authorize the recovery plan and process but during the initial recovery process they will most likely be heavily involved in other matters.
Contribute your Thoughts:
Chosen Answer:
This is a voting comment (?). You can switch to a simple comment. It is better to Upvote an existing comment if you don't have anything to add.
Submit