A supply manager identifies an overseas source for parts used by the organization. The supplier's capacity, performance, reputation and sample quality are all acceptable. During final price negotiations, the supplier requests that the contract be based on its local currency. Which of the following is the FIRST course of action the supply manager should take in order to address the possible impact of this request?


A.

Reject the request based on the uncertainty of future pricing


B.

Propose a limit on the range of fluctuations allowed


C.

Perform exchange rate due diligence with the help of a financial advisor


D.

Re-focus the discussion on other issues before addressing the request