A local utility's supply manager is preparing a solicitation to select a contractor to construct a controlling station for the utility's main plant. Construction must begin within four months and be completed in a year or less, as delays in bringing the new station online could cause serious losses for the utility. Which of the following will be MOST effective in monitoring performance and ensuring timely completion?