ISM INTE Question # 3 Topic 1 Discussion

INTE Exam Topic 1 Question 3 Discussion:
Question #: 3
Topic #: 1

A supplier with a previously good performance record has recently been shipping parts with a number of flaws, making them unusable for production. The firm’s supply manager would like to resolve these problems before taking more drastic measures. Which of the following actions should the supply manager take FIRST’


A.

Explore possible root causes, including changes in the supplier's production processes


B.

Ask engineering to review tolerances on non-critical specifications and relax them if possible


C.

Test the parts at an independent laboratory and notify the supplier of the results


D.

Re-work the parts in-house and bill the supplier for any costs incurred