ISTQB Certified Tester Advanced Level Test Management (CTAL-TM) v3.0 CTAL-TM Question # 1 Topic 1 Discussion

CTAL-TM Exam Topic 1 Question 1 Discussion:
Question #: 1
Topic #: 1

You are Test Manager for a project which is in the Test Implementation stage for the first planned iteration, creation of the initial Test Cases and required test data is progressing well.

The Test Strategy documents the Stakeholders view that small teams should collaborate together to create and test functionality which is to be released in iterations, with each release building on the success of the last.

Stakeholders are willing to accept the risks of a partly working system in the early stages. Delivery of working functionality (particularly around interfaces to third party systems and performance of back end databases) is the priority for the early releases.

Which of the following test types would you select for this first planned iteration, in order to meet Stakeholders expectations?

a) Usability testing

b) Structural testing

c) Functional testing of process flows

d) Performance testing

e) Business process testing

f) Component integration testing

You are Test Manager for a project which is in the Test Implementation stage for the first planned iteration, creation of the initial Test Cases and required test data is progressing well.

The Test Strategy documents the Stakeholders view that small teams should collaborate together to create and test functionality which is to be released in iterations, with each release building on the success of the last.

Stakeholders are willing to accept the risks of a partly working system in the early stages. Delivery of working functionality (particularly around interfaces to third party systems and performance of back end databases) is the priority for the early releases.

Which of the following test types would you select for this first planned iteration, in order to meet Stakeholders expectations?

a) Usability testing

b) Structural testing

c) Functional testing of process flows

d) Performance testing

e) Business process testing

f) Component integration testing


A.

b, c, d and f.


B.

b, d, e and f.


C.

a. b, d and f.


D.

a, c, d and e.


Get Premium CTAL-TM Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
CTAL-TM practice test questions answers