Question #: 11
Topic #: 2

Refer lo SCENARIO 2 - You are writing the Master Test Plan for Project 2 and must include a section documenting project risks that you believe could impact testing along with how, as Test Manager, you propose to manage each risk.

Which one of the following is the MOST appropriate entry for the Master Test Plan for RISK 4 "The user interface software for the sound systems will be delivered late into testing-?

SELECT ONE OPTION


A.

Ask the stakeholders to accept the risk without mitigation, as code is often late


B.

Prepare the testers to work longer hours


C.

Accept the risk and develop a contingency plan


D.

Transfer the risk to Smart Alarms for them to propose mitigation