ISTQB Foundation Level CTFL-Foundation Question # 18 Topic 2 Discussion

CTFL-Foundation Exam Topic 2 Question 18 Discussion:
Question #: 18
Topic #: 2

Your task is to compile a test execution schedule for the current release of software.

The system specification states the following logical dependencies:

• An admin user must create/amend/delete a standard user.

• A standard user is necessary to perform all other actions.

The test plan requires that re-tests must be performed first, followed by the highest priority tests. To save time, the test plan states that tests should be scheduled to create test data for the subsequent tests in the schedule.

The following test cases have been designed, with an indication of priority (1 being the highest priority) and whether the test has previously failed.

CTFL-Foundation Question 18

Which test execution schedule meets the test plan requirements and logical dependencies?


A.

a, d, c, b, e


B.

a, c, b, d, e


C.

e, a, b, c, d


D.

e, a, d, c, b