ISTQB Foundation Level ISTQB-CTFL Question # 93 Topic 10 Discussion

ISTQB-CTFL Exam Topic 10 Question 93 Discussion:
Question #: 93
Topic #: 10

Your organization's test strategy states that it is desirable to use more than one method for estimating test effort. You are responsible for estimating test effort for the next project. Based on historical data, the development-to-test effort ratio is 5:3.

The initial estimate for the development effort is 450 person-days.

Which ONE of the following options corresponds to the estimated test effort using the ratio-based method?


A.

750 person-days


B.

180 person-days


C.

720 person-days


D.

270 person-days