Which ONE of the following options is a PRODUCT risk and NOT a PROJECT risk?


A.

Incorrect calculation logic in the software, leading to inaccurate results.


B.

Poor communication between team members, making project management more difficult.


C.

Staff shortages in the project leading to scheduling problems.


D.

Delays in the delivery of work products by the project team.