Question #: 81
Topic #: 9

A Test Manager conducts risk assessment for a project. One of the identified risks is: The sub-contractor may fail to meet his commitment". If this risk materializes. it will lead to delay in completion of testing required for the current cycle.

Which of the following sentences correctly describes the risk?


A.

It is a product risk since any risk associated with development timeline is a product risk.


B.

It is no longer a risk for the Test Manager since an independent party (the sub-contractor) is now managing it


C.

It is a object risk since successful completion of the object depends on successful and timely completion of the tests


D.

It is a product risk since default on part of the sub-contractor may lead to delay in release of the product