Question #: 5
Topic #: 1

In a Mule project, Flow-1 contains a flow-ref to Flow-2 depends on data from Flow-1 to execute successfully.

Which action ensures the test suites and test cases written for Flow-1 and Flow-2 will execute successfully?


A.

Chain together the test suites and test cases for Flow-1 and Flow-2


B.

Use ‘’Set Event to pass the input that is needed, and keep the test cases for Flow-1 and Flow-2 independent


C.

Use ‘’Before Test Case’’ To collect data from Flow-1 test cases before running Flow-2 test cases


D.

Use ‘After Test Case’ to produce the data needed from Flow-1 test cases to pass to Flow-2 test cases