NAHQ CPHQ Certification CPHQ Question # 123 Topic 13 Discussion

CPHQ Exam Topic 13 Question 123 Discussion:
Question #: 123
Topic #: 13

An organization IsImplementing a new electronic medical record and has employed a project manager. At the first meeting, the project manager observes the following:

• The team estimates It Is one-fourth finished with Identifying benchmark organizations.

• Team members have not yet begun to identify the current state.

- They are halfway through collecting public data, which puts them slightly behind schedule for that task.

Which of the following tools should the quality Improvement project manager recommend?


A.

Model for Improvement


B.

Design of Experiments


C.

Gantt chart


D.

Ishlkawa diagram