Question #: 157
Topic #: 16

A performance Improvement team has been meeting to examine delays in getting admissions from theemergency room to the nursing units. After six months of collecting data, the upper control limit was ISO minutes, and the lower control limit was 60 minutes. The next month's data shows a time of 155 minutes. The team should understand that this represents what type of variation?


A.

standard


B.

random


C.

common cause


D.

special cause