IEPPE Exam Topic 3 Question 22 Discussion:
Question #: 22
Topic #: 3

It can take a lot of time to construct a new building, and often legislation, codes, or standards will change during that time. With which codes must the end design be compliant?


A.

The end design must meet the requirements that are in place at the end of the process.


B.

The end design must meet the requirements that were in place when permits were issued.


C.

The end design must meet requirements that were in place when they broke ground.


D.

The end design must meet requirements that were in place when the contract was signed.