Question #: 64
Topic #: 7

Before development, your team creates a spreadsheet with work items to populate the backlog. All work items that describe business requirements are prioritized as Must have. You also create work items to address:

A future enhancement request to group a set of existing steps into a multistep form

A drop-down list that is missing one of the required options — This work item is in progress because the missing option prevents work from being done

How do you populate the backlog directly from the spreadsheet?


A.

Create bugs


B.

Create feedback


C.

Import stories


D.

Create stories