Pegasystems Certified Senior System Architect PEGACPSSA23V1 Question # 16 Topic 2 Discussion

PEGACPSSA23V1 Exam Topic 2 Question 16 Discussion:
Question #: 16
Topic #: 2

An assignment service-level agreement (SLA) is configured with the following details:

♦ Initial urgency: 20

♦ Assignment ready: Timed delay of 2 hours

♦ Goal: 5 hours and increase urgency by 10

♦ Deadline: 2 hours and increase urgency by 25

♦ Passed deadline: 1 hour, increase urgency by 5, and limit events to 6

The case reaches the assignment at 9 AM on Wednesday.

Assuming no other urgency adjustments, what is the assignment urgency 6.5 hours after the case reaches the assignment?


A.

85


B.

95


C.

75


D.

80