PeopleCert MSP MSP-Practitioner Question # 2 Topic 1 Discussion

MSP-Practitioner Exam Topic 1 Question 2 Discussion:
Question #: 2
Topic #: 1

Which of the following is an activity in Defining a Programme?


A.

Design the Projects Dossier


B.

Manage transition


C.

Produce the Programme Brief


D.

Align the projects with benefits realization