Weekend Special Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: simple70

Exam CAPM All Questions
Exam CAPM All Questions

View all questions & answers for the CAPM exam

PMI CAPM CAPM Question # 4 Topic 1 Discussion

CAPM Exam Topic 1 Question 4 Discussion:
Question #: 4
Topic #: 1

Which of the following processes are part of the Project Integration Management Knowledge Area?


A.

Develop Project Management Plan, Collect Requirements, Create WBS


B.

Develop Project Management Plan, Control Scope, Develop Schedule


C.

Develop Project Charter, Define Scope, Estimate Costs


D.

Develop Project Charter, Direct and Manage Project Execution, Close Project or Phase


Get Premium CAPM Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.