Weekend Special Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: simple70

Exam CAPM All Questions
Exam CAPM All Questions

View all questions & answers for the CAPM exam

PMI CAPM CAPM Question # 5 Topic 1 Discussion

CAPM Exam Topic 1 Question 5 Discussion:
Question #: 5
Topic #: 1

Which illustrates the connection between work that needs to be done and its project team members?


A.

Work breakdown structure (WBS)


B.

Network diagrams


C.

Staffing management plan


D.

Responsibility assignment matrix (RAM)


Get Premium CAPM Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.