The zero duration of milestones in project planning occurs because milestones:


A.

Are unpredictable and challenge the Plan Schedule Management process.


B.

Occur at random times in the project plans.


C.

Represent a moment in time such as a significant project point or event.


D.

Represent both significant and insignificant points in the project and are difficult to anticipate.