Weekend Special Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: simple70

Exam CAPM All Questions
Exam CAPM All Questions

View all questions & answers for the CAPM exam

PMI CAPM CAPM Question # 111 Topic 12 Discussion

CAPM Exam Topic 12 Question 111 Discussion:
Question #: 111
Topic #: 12

The following is a network diagram for a project.

CAPM Question 111

The free float for Activity E is how many days?


A.

2


B.

3


C.

5


D.

8


Get Premium CAPM Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.