PMI CAPM CAPM Question # 124 Topic 13 Discussion

CAPM Exam Topic 13 Question 124 Discussion:
Question #: 124
Topic #: 13

Which document in the project management plan can be updated in the Plan Procurement Management process?


A.

Budget estimates


B.

Risk matrix


C.

Requirements documentation


D.

Procurement documents