PMI CAPM CAPM Question # 97 Topic 13 Discussion

CAPM Exam Topic 13 Question 97 Discussion:
Question #: 97
Topic #: 13

What is the difference between verified and accepted deliverables?


A.

Accepted deliverables have been completed and checked for correctness; verified deliverables have been formally approved by the customer or authorized stakeholder.


B.

Accepted deliverables have been inspected by the quality team; verified deliverables are outputs from the Validate Scope process.


C.

Accepted deliverables have been formally signed off and approved by the authorized stakeholder; verified deliverables have been completed and checked for correctness.


D.

Accepted deliverables have been formally accepted by the project manager; verified deliverables are the outputs from the Control Quality process.