The project manager is working with some functional managers and stakeholders on the resource management plan Which elements may be included in this plan?


A.

Team values, team agreements, and conflict resolution process


B.

Conflict resolution process, communication guidelines, and meeting schedules


C.

Team roles and responsibilities, team management, and training plan


D.

Resource requirements, resource assignments, and team performance assessments