Which of these is true of project integration management?


A.

Project Integration Management is mandatory and more effective in larger projects.


B.

Project Integration Management and expert judgment are mutually exclusive.


C.

Project Integration Management is the responsibility of the project manager


D.

Project Integration Management excludes the triple constraints if cost performance index (CPI) equals zero.