PMI CAPM CAPM Question # 156 Topic 16 Discussion

CAPM Exam Topic 16 Question 156 Discussion:
Question #: 156
Topic #: 16

When addressing roles and responsibilities,which item ensures that the staff has the skills required to complete project activities?


A.

Authority


B.

Role


C.

Competency


D.

Responsibility