Question #: 13
Topic #: 2

The Verify Scope process is primarily concerned with:


A.

formalizing acceptance of the completed project deliverables.


B.

accuracy of the work deliverables.


C.

formalizing approval of the scope statement.


D.

accuracy of the work breakdown structure (WBS).