Weekend Special Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: simple70

Exam CAPM All Questions
Exam CAPM All Questions

View all questions & answers for the CAPM exam

PMI CAPM CAPM Question # 16 Topic 2 Discussion

CAPM Exam Topic 2 Question 16 Discussion:
Question #: 16
Topic #: 2

A work package has been scheduled to cost $1,000 to complete and was to be finished today. As of today, the actual expenditure is $1,200 and approximately half of the work has been completed. What is the cost variance?


A.

-700


B.

-200


C.

200


D.

500


Get Premium CAPM Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.