PMI CAPM CAPM Question # 221 Topic 24 Discussion

CAPM Exam Topic 24 Question 221 Discussion:
Question #: 221
Topic #: 24

Which of the following correctly explains the term "progressive elaboration'?


A.

Changing project specifications continuously


B.

Elaborate tracking of the project progress


C.

Elaborate tracking of the project specifications with a change control system


D.

Project specifications becoming more explicit and detailed as the project progresses