PMI CAPM CAPM Question # 241 Topic 26 Discussion

CAPM Exam Topic 26 Question 241 Discussion:
Question #: 241
Topic #: 26

Which document can help a project manager to leverage historical project information?


A.

Lessons learned register


B.

Schedule baseline


C.

Work performance data


D.

Deliverable acceptance forms


Get Premium CAPM Questions

Contribute your Thoughts:


Chosen Answer: