PMI CAPM CAPM Question # 251 Topic 27 Discussion

CAPM Exam Topic 27 Question 251 Discussion:
Question #: 251
Topic #: 27

Given the following information, what is the schedule variance (SV) for this project?

    Early start date (ES): 16 weeks

    Actual time: 12 weeks

    Schedule performance index (SPI): 1.3


A.

5


B.

2


C.

3


D.

4