PMI CAPM CAPM Question # 268 Topic 27 Discussion

CAPM Exam Topic 27 Question 268 Discussion:
Question #: 268
Topic #: 27

In an agile or adaptive environment. when should risk be monitored and prioritized?


A.

Only during the initiation and Closing phases


B.

During the initiation and Planning phases


C.

During each iteration as the project progresses


D.

Throughout the Planning process group and retrospective meeting