PMI CAPM CAPM Question # 288 Topic 29 Discussion

CAPM Exam Topic 29 Question 288 Discussion:
Question #: 288
Topic #: 29

What does an S-curve from a Monte Carlo analysis show?


A.

Cumulative probability distribution representing probability of achieving a particular outcome


B.

Individual project risks or uncertainties that have the most potential impact on outcome


C.

Best alternative out of the possible solutions, incorporating associated risks and opportunities


D.

Diagram for all project uncertainties and their influence over a period of time