PMI CAPM CAPM Question # 311 Topic 32 Discussion

CAPM Exam Topic 32 Question 311 Discussion:
Question #: 311
Topic #: 32

Change requests are an output from which Project Integration Management process?


A.

Direct and Manage Project Execution


B.

Develop Project Management Plan


C.

Close Project


D.

Develop Project Charter