PMI CAPM CAPM Question # 316 Topic 33 Discussion

CAPM Exam Topic 33 Question 316 Discussion:
Question #: 316
Topic #: 33

A project charter is an output of which Process Group?


A.

Executing


B.

Planning


C.

Initiating


D.

Closing