PMI CAPM CAPM Question # 343 Topic 35 Discussion

CAPM Exam Topic 35 Question 343 Discussion:
Question #: 343
Topic #: 35

Which tools or techniques are used during the Close Project or Phase process?


A.

Reserve analysis and expert judgment


B.

Facilitation techniques and meetings


C.

Expert judgment and analytical techniques


D.

Performance reviews and meetings