PMI CAPM CAPM Question # 382 Topic 39 Discussion

CAPM Exam Topic 39 Question 382 Discussion:
Question #: 382
Topic #: 39

Which of the following is an input to the Develop Project Charter process?


A.

Work performance information


B.

Project management plan


C.

Business case


D.

Change requests