Summer Certification Special Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: validbest

Exam CAPM All Questions
Exam CAPM All Questions

View all questions & answers for the CAPM exam

PMI CAPM CAPM Question # 400 Topic 41 Discussion

CAPM Exam Topic 41 Question 400 Discussion:
Question #: 400
Topic #: 41

A logical relationship in which a successor activity cannot start until a predecessor activity has finished is known as:


A.

Start-to-start (SS).


B.

Start-to-finish (SF).


C.

Finish-to-start (FS).


D.

Finish-to-finish (FF).


Get Premium CAPM Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.