CAPM Exam Topic 42 Question 412 Discussion:
Question #: 412
Topic #: 42

A project manager at a publishing company decides to initiate the editing phase of the project as soon as each chapter is written. Which type of Sequence Activities tool and technique is involved, considering that there was a start-to-start relationship with a 15-day delay?


A.

Slack


B.

Float


C.

Lag


D.

Lead