PMI CAPM CAPM Question # 415 Topic 42 Discussion

CAPM Exam Topic 42 Question 415 Discussion:
Question #: 415
Topic #: 42

An output of the Direct and Manage Project Work process is:


A.

Deliverables.


B.

Activity lists.


C.

A work breakdown structure.


D.

A scope statement.