PMI CAPM CAPM Question # 442 Topic 45 Discussion

CAPM Exam Topic 45 Question 442 Discussion:
Question #: 442
Topic #: 45

The process of identifying specific actions to be performed to produce project deliverables is:


A.

Define Activities.


B.

Create WBS.


C.

Define Scope.


D.

Develop Schedule.