PMI CAPM CAPM Question # 44 Topic 5 Discussion

CAPM Exam Topic 5 Question 44 Discussion:
Question #: 44
Topic #: 5

Which of the following tools or techniques is used for Estimate Activity Durations?


A.

Critical path method


B.

Rolling wave planning


C.

Precedence diagramming method


D.

Parametric estimating